Big Sandy Drive at Long Hollow Creek Low Water Crossing
Improve existing low water crossing to all-weather crossing

Precinct Location
Sponsored by Precinct Three
Project Description
Current low water crossing floods frequently and cuts off access to the subdivision, completely after even small amount of rain. The new bridge will be a two lane bridge at a higher elevation which will clear a 10-25 year event. Design is in 30%-90% Phase. Different Alternatives are being explored regarding the Traffic Control Plan. Temporary detour upstream would take out the wetlands, and downstream detour would require removal of a heritage tree and major trimming of a larger private heritage tree.
Funding Source
2011 bond funds