Bee Creek Road Improvements

Bee Creek Road Improvements

Widen existing 2-lane road to 4-lane arterial from SH 71 to Highland Boulevard

Current Phase

Precinct Location

Sponsored by Precinct Three

Project Description

This project will realign Bee Creek Road to improve sharp curves and connect to existing Highland Boulevard tie back to Bee Creek Road. This improvement from a two lane to four lane road will increase capacity of Bee Creek Road from Highland Boulevard and will allow for traffic in and out of the subdivisions. Under construction, 50% complete.

Funding Source

97 bond funds for design. 2011 bond funds for constructions and ROW.