Arterial A (Engineering and ROW)
New MAD 4 arterial between US 290 East and Parmer Lane
Precinct Location
Sponsored by Precinct One
Project Description
Project is in the 90% design phase. Waste Management has not yet issued permit to the County's geotech sub to drill bore holes on its property. Limited funding available for ROW acquisition and no funding available for construction. Estimated construction cost for Travis County's portion, $23.5 million. Additional water line easement through WM property is required for the relocation of the City of Pflugerville's water line in conflict with a bridge abutment.
Funding Source
2009 CO's for engineering, 2011 Bond for final design and ROW.